Construction Manager: EAGA Company, LLc
Architect: TMH Associates
Engineer: Guest Engineering
Contractor: EAGA Company, LLC
Location: Philadelphia, PA
Demolition phase in preparation of 3rd floor addition and interior alterations
Assessment of existing joist pockets to level 2nd floor
Lower joist pockets indicate level of existing roof now removed
and to be abandoned
Assessment of existing roof rafters to be removed and replaced
in preparation of new new rubber roofing system for entire 3rd floor roof.
Inquiries about this project can be directed to Eric A. Godbolt at 215-395-6220
To follow this project updates, Project 5262011